~18 lb units — one-person stacking, ground-row curing at wall height
QC loop: gauge every cycle · thickness/flatness every 20th · drop test every 50th · key-fit every batch
The press IS the crush rig — gauge at failure = MPa
The Brick Cycle — Soil In, Brick Out
1 DOSE — soil into the bore2 PRESS — platen to dead-stop3 RETRACT — platen up4 SHOE OUT — bottom opens5 EJECT — platen pushes through6 TAKE-OFF — shelf → stack
Cycle ~20–40 s/brick powered · bottom shoe IS the mold floor — slide it out, platen pushes the brick through to the bed; front door drops open = take-off shelf at bed level, pull brick over it → stack
Automation — $300 Spec, ~$60 Scrounged
Item
New
Scrounged
Valve actuator (junkyard linear actuator on stock lever)
Mound + view-dormer: framed 48×30″ reveal through ~14″ of flank soil — true outside view · oculus cap ring at apexRimmed open run + sump + threshold sill → covered vault → doorway never sky-exposed
Pit floor 36″ below grade → springs from raised collar → 12″ wall + 24″ base band (below grade) → corbel to brick cap → oculus + two 48″ view-dormers (~2 ft shafts — deep reveals, true view) → tholos stomion: stairs under a corbelled vault
The Venue Module — Unburied, No Mound
Interactive — drag to orbit, wheel to zoom, buttons for Exterior/Section/Wireframe/Top. THE GATEHOUSE — earth-sheltered TWO-CELL vaulted gatehouse centered on the square — 14×8-ft hall + 14×5-ft livable back cell behind a shared party wall (door through it; rear vault leans FORWARD onto it — opposing thrust cancels, the multi-bay trick the Dunes basilica repeats; thin liner rear wall — the bank closes the arc): Nubian leaning vault (no formwork) under a soil cap + spring-height berms (27°, placed BEFORE the vault — they carry the thrust) + plinth keys + one continuous counterforts + haunch banks → ~5 g composite-kern bound (cad/venue_battle.py — computed 10–12 g, contingent on compacted lifts + keys) + fully open 14-ft arched mouth under a stepped arch-ring face — the facade's silhouette follows the vault's own arc (retains the cap, no square wall, no vertical soil face) — the echea bass vents moved INTO the rib walls (~56 Hz, woofer discs flanking the entrance = the walls ARE the PA), centered on the square — dancers on bare earth, no pad. ~3,050 units + ~55 yd3 scrape-earth ≈ ~9–11 d all-in, NO machine (counterforts replace the deep bank; jumbo bricks on the same press) w/ pre-pressed bricks + excavator. Dome deferred to Trip 2 (2.67 g dry / 2.18 g wet when built)
The Gatehouse — What's Inside
Nubian leaning vault 14×8 ft — vertical front arch + 11 courses at ~15°, each leaning on the last → full 14-ft span, zero formwork; ~200 sq ft covered floor, two cells (hall + livable back cell — the party wall's door links them)
Ribs + party wall + rear cell — deep-battered wythe+soil-core walls; the party wall's gable is the shared abutment BOTH vaults lean into (rear cell's courses lean FORWARD — opposing thrust cancels); rear gable wall + vent stack = a livable second room
Earth-shelter — load-bearing — berms (~27°) cresting over springing + ~20″ crown cap + mouth wings (the open face gets a kern) + plinth keys below grade (kills sliding → kern rocking); berms go in BEFORE the vault — they carry the thrust
Fully open mouth + arched front ring — the 14-ft arch free-spans rib-to-rib, nothing in the doorway; the spandrel steps along the vault's own arc (one arched face, no square wall) and still retains the cap
Echea bass vents ×2 — in the RIBS — ~44 L Helmholtz cavities embedded in each rib's soil-core zone, necks + dark woofer discs on the front faces ≈ 56 Hz → the walls ARE the subwoofers (passive ports)
Dust-storm package — mouth threshold (saltation lip) + masonry vent stack through the cap + paver armor on the crest + echea shutters: seal the hall, live in the back cell
No pad — gatehouse centered on the square; dancers on bare site earth; vent shutters = the acoustic "mute"
Honest rating: ~5 g composite-kern bound — battle-tested (venue_battle.py: computed 10–12 g, contingent on compacted lifts + plinth keys + wings; incoherent-soil floor ~1.6 g; Salton liquefaction flagged) / unburied ribs FAIL static thrust — shelter is structural; dome = Trip 2 at 2.67 g dry / 2.18 g wet; 32-ft dance dome = crew build
Build Sequence — ~5 Days On Site
Day 1: test hole ✓ → excavate ~36″ pit · swale + levee same day
Day 2–3: press ~2,100 keyed units at pit edge
Day 3–5: compass arm → spiral courses · clay-dust bedding · place-don't-drop · level each course
Day 6: paver floor · apron skirt · mound berm — spoil self-funds it · drain daylighted
TRUE helix spiral (igloo): each brick ~H/n higher than the last — bears on course below + previous block, self-supporting at placement
Corbel 1–3″/course · hemispherical · 12″ wall + 24″ base band (courses 0–7, below grade) · +20 kN cap · batter
Flat beds + keyed insert ALL courses — single SKU, no course-tracking
Fallback: sand mound only if free corbelling proves too fussy
Water Defense — 7 Layers, All On-Site
1 Siting — highest ground, never in a "dry" wash
2 Diversion swale — contour ditch around both sides; spoil = levee; doubles as permaculture water harvest
3 Rim collar 12–18″ — floor below grade, springline above — sheet flow can't climb in
4 Flared apron — kills splash/ponding
5 Air-gap lining — 1–2″ void behind wall (better than rubble, zero material) + drain channel to daylight
6 Covered entry — stomion vault — corbelled vault roofs the inner stair run through the berm: doorway never sky-exposed; open outer run → drain sump; raised sill lip at door
7 Infiltration floor — loose pavers + coarse sand
Residual: catastrophic flood → ~free soil + 3 days = rebuildable by design
Disaster Scorecard — Full Ancestral Toolkit
Threat
Defense
Seismic — VERIFIED PASS 5.0g
12″ wall + 24″ base band · keys ALL courses · helix spiral · mound w/ 12″ cap · pit-buttress + soil-shear credits. ~1.7× the strongest recorded motion ever (~3g). Site ceiling = liquefaction susceptibility, not structure
Fire
Best-in-class — earth doesn't burn
Flood
7-layer system; inundation remains fatal — siting IS the answer
Igloo · clochán · trullo · tholos — every proven dry-stack technique, zero tensile elements, ~100% site soil, uniform units throughout
Cost · Schedule · Next Actions
Phase
$
0 — soil gates (jars + soak tests)
~20
1 — working plant
~460–635
2 — first dome standing
+68–108
3 — throughput parity pkg
+450–900
4 — movers (per region, optional)
2.5–15k
5 — automation (donor scrounge + Nano)
+40–90
W1: messages + buy run + soil tests + test hole
W2: weld mold + mount on beam + plumb
W3–4: tune, durability gates, ~2,100 units
~5–6 days: excavate → press → stack → mound → dome · strikes in ~4–6 h: remote-pole collapse into the pit (15-ft exclusion, nobody on the shell), mound backfills on top — returns to land clean · or ~1 day careful unstack to reuse bricks